Below is a practical, engineer-focused guide to designing a high-efficiency PV system — from initial site assessment through component selection, layout, controls, and expected performance. I include a worked example (100 kW DC system) with digit-by-digit arithmetic so you can see how numbers were derived.
1) Project goals & constraints (start here)
- Purpose: grid-tied generation, off-grid, hybrid backup? (affects battery + inverter choice)
- Target capacity / energy need: e.g., supply building load, reduce grid draw, export.
- Site constraints: available area, orientation, shading, local regulations, interconnection rules.
- Budget & lifecycle: CAPEX target, expected O&M budget, ROI/horizon.
- Climate: PV irradiance, ambient temperature, dust/soiling rates — these strongly affect design choices.
2) Site assessment & resource data
- Obtain hourly/daily GHI/POA irradiance for the site (satellite data, local met station, or PVGIS/PVWatts).
- Measure or map shading (trees, chimneys, nearby buildings) using tools or a drone survey (image provided helps visualise large farms).
- Determine local ambient temperature range — high temps reduce panel output.
3) Key system design choices that drive efficiency
- Panel technology: high-efficiency monocrystalline (TOPCon, PERC, HJT) for best power density.
- Panel heat performance: low temperature coefficient (-0.25%/°C or better) reduces losses in hot climates.
- Tracking: single-axis trackers increase annual yield (10–25%) but add CAPEX and maintenance — in dusty/land-constrained sites trackers often pay off.
- Inverter topology: string inverters with multiple MPPTs or central inverters depending on scale and shading. For partial shading, choose microinverters or power optimizers.
- System voltage: higher DC strings reduce IO losses but must match panel Voc and safety limits.
- Balance of System (BOS): low-loss cabling, quality junction boxes and connectors, proper grounding and surge protection.
4) Loss model & expected performance (typical derates)
Consider typical loss categories and choose conservative values for a high-efficiency target:
- Soiling: 2–8% (depends on dust; in dusty regions, plan for 4–8%).
- Temperature: depends on module temp coefficient and site ambient.
- Module mismatch and degradation: ~1–3%.
- Inverter efficiency: modern string inverters 98–99% at rated.
- Wiring and transformer losses: 1–3%.
Performance Ratio (PR) is a convenient single metric: high-efficiency systems aim for PR = 0.78–0.85 (clean, well-designed systems often reach 0.82–0.85).
5) Worked example — design a 100 kW DC (array) system
Assumptions
- Target DC nameplate = 100 kW.
- Panel choice = 400 W nominal (mono PERC/TOPCon) with area ≈ 1.95 m² each.
- Site average daily sun (H) = 5.0 kWh/m²/day (typical for many tropical locations).
- Performance Ratio (PR) = 0.75 (conservative for dusty/hot site); you can improve this with better cleaning, cooling, and low-temp-coeff modules.
Panel count
- DC capacity / panel power = 100,000 W ÷ 400 W = 250 panels.
- Calculation digit by digit: 100,000 ÷ 400 = 250.
Area estimate
- Panel area × count = 1.95 m² × 250 = 487.5 m².
- Calculation: 250 × 1.95 = 250 × (2.00 − 0.05) = 500 − 12.5 = 487.5 m².
Allow 25–40% extra for access aisles and spacing if using fixed tilt, more if trackers: so site footprint ≈ 610–680 m² (depending on layout and row spacing).
Annual energy yield estimate
Use: Annual energy (kWh) = DC_kW × H (kWh/m²/day) × 365 × PR.
- First compute H × 365: 5.0 × 365 = 1,825.
- Multiply by PR 0.75: 1,825 × 0.75 = 1,368.75 (this is specific yield in kWh/kW-yr).
- Multiply by system size 100 kW: 1,368.75 × 100 = 136,875 kWh/year.
- All arithmetic done stepwise above.
If you can raise PR to 0.82 and H is 5.5, new estimate:
- 5.5 × 365 = 2,007.5; × 0.82 = 1,646.15 kWh/kW-yr; × 100 kW = 164,615 kWh/yr.
Inverter sizing
- Choose inverter(s) with total AC capacity slightly smaller than DC (DC:AC ratio typically 1.1–1.3). For 100 kW DC, choose ~80–90 kW AC (for DC:AC = 1.11 → 90 kW AC). Higher DC:AC improves energy harvest on low-irradiance days but may clip at peak irradiance.
- Use multiple string inverters with multiple MPPTs to reduce mismatch from shading or orientation differences. Example: three 33 kW inverters or 2 × 50 kW string inverters depending on product availability.
Strings & voltage
- If Vmp panel ≈ 33 V (typical depends on panel type), string length for a 600 V max system: 600 ÷ 33 ≈ 18 strings per string — but obey Voc at coldest temp. Use manufacturer Voc and site coldest temp to verify. Safety margins required.
Cabling & IO losses
- Aim for DC cable losses <1.5–2%: choose cable sizes for <1–2% drop at max current. Use centralized combiner boxes where efficient.
6) Maximise efficiency — practical measures
- Select modules with high STC efficiency and low temperature coefficient. Pay for panels with better long-term degradation warranties (≤0.5%/yr).
- Minimize soiling losses: automated wash systems, scheduled manual cleaning, or hydrophobic coatings.
- Use multiple MPPTs or module-level power electronics for partially shaded sites.
- Optimize tilt & orientation: tilt ≈ latitude for annual yield; adjust slightly for seasonal optimisation or to reduce soiling accumulation. For Tanzania (latitude ≈ 6–11°S), tilt is small (≈6–11°) — but slightly higher tilt helps cleaning by rain.
- Cooling and ventilation: ensure free airflow behind modules; elevated mounts reduce module temperature. Avoid rooftop hot spots.
- Use high-efficiency inverters and ensure they operate near high-efficiency points most hours (right sizing, not too oversized).
- Consider single-axis tracking if land allows — increases yield but ensure maintenance plan for trackers in dusty environments.
7) Controls, monitoring & smart features
- Monitoring: per-inverter and ideally per-string/module level (if critical). Log irradiance, module temp, array current/voltage, inverter AC power. Telemetry for alarms.
- MPPT strategy: multiple MPPTs with dynamic MPPT mapping; in complex shading use ML-based MPPT optimizers if budget allows.
- Curtailment & grid codes: ensure anti-islanding, ramp rate control, reactive power capability per local grid code.
- Energy management: integrate with battery storage/EMS for peak shaving, frequency response, and maximizing self-consumption.
8) Construction & BOS considerations
- Mechanical: durable racking (corrosion-resistant), correct ballast for wind loads, proper torque and fasteners. Follow local standards for wind/structural loads.
- Electrical safety: surge arrestors (DC and AC), rapid shutdown, compliant earthing and lightning protection.
- Permits & interconnection: verify required documentation and grid interconnection capacity limits.
- O&M plan: preventive maintenance schedule, cleaning frequency, vegetation control, spare parts stock (inverters, fuses), SCADA alerts.
9) Economics & lifecycle
- Model LCOE considering CAPEX, OPEX, degradation rate (e.g., 0.5%/yr), financing, incentives. Higher initial CAPEX on premium panels and trackers often pays back via higher specific yield. Run sensitivity analyses on PR, degradation, and irradiation.
10) Simulation & verification (MATLAB / PVsyst / Homer)
- PVsyst is the go-to for detailed yield and shading analysis (single-axis tracker, string layout, string configuration).
- MATLAB / Simulink: simulate MPPT algorithms, inverter control, PV model using one-diode equations.
- Quick MATLAB approach: model panel I–V using manufacturer Isc, Voc, Imp, Vmp and temperature coefficients; implement MPPT (e.g., Perturb & Observe or Incremental Conductance); simulate under time-series irradiance and temperature to estimate energy and clipping.
- Validate the system with hourly resource data and perform sensitivity runs for soiling, temperature and tilt.
11) Example single-line (simplified)
PV array → DC combiner(s) → DC disconnects → inverter(s) (multiple MPPTs) → AC distribution panel → transformer (if needed) → grid point of interconnection / load. Include surge protection and monitoring tap points.
12) Checklist before handover
- Commissioning report: I–V curves, inverter tests, insulation tests, earthing resistance.
- Performance acceptance test: compare measured PR and yield to modeled expectations.
- O&M manual and spare parts.
- Safety signage and access permissions.
Quick summary (what to prioritize for high efficiency)
- High-efficiency panels with low temp coefficient.
- Low loss BOS (large system voltage, proper conductor sizing).
- Multiple MPPTs / module-level control for shading.
- Effective soiling management and ventilation to reduce temperature.
- Smart monitoring + commissioning + regular O&M.
If you want, I can:
- Convert the example into a full BOM + cost estimate (modules, inverters, mounting, cabling) for your local market; or
- Produce a PVsyst project file checklist or a MATLAB starter script to simulate annual yield using your exact site GHI and temperature time series.
Which of those would be most useful next?